SCC Turn Tracker
As stated in the South Campus Commons lease, entries can happen any day during this time between 8 AM and 8 PM, 7 days a week. This will include completion of work, inspections, and go-backs and touch ups based on those inspections.
Below the calendars are up-to-date trackers. These trackers indicate when an entire building is completed; so they may not fully reflect if your individual apartment has been visited for the given trade, yet. These are updated daily, so there could be a lag from work completed the previous day. These are meant to give an estimate of where the crews are in the process and do not reflect when teams need to go back to units based on individual inspection results.
The South Campus Commons team thanks you for your cooperation and understanding during the lease transition period, as we all work together to provide a welcoming environment to our incoming residents.


Building 1

Building 1 Turn Tracker
Maintenance
July 29 – August 1
Painting
August 3 – 5
Cleaning
August 7 – 9
Carpet Cleaning
August
12 – 13
Final Inspection
August 14 – 15
Maintain move-in ready
& Maintenance Go-backs
August 15 – 21

Building 2

Building 2 Turn Tracker
Maintenance
August 2 – 3
Painting
August 5 – 6
Cleaning
August 9
Carpet Cleaning
August 13
Final Inspection
August 14
Maintain move-in ready
And Maintenance Go backs
August
16 – 21

Building 3

Building 3 Turn Tracker
Maintenance
August 4 – 6
Painting
August 7 – 9
Cleaning
August 10 – 12
Carpet Cleaning
August 14 – 16
Final Inspection
August 16
Maintain move-in ready
& Maintenance go backs
August
16 – 21

Building 4

Building 4 Turn Tracker
Maintenance
August 7 – 8
Painting
August 9 – 10
Cleaning
August 12
Carpet Cleaning
August 14 – 16
Final Inspection
August 15
Maintain move-in ready
& Maintenance go backs
August
16 – 21

Building 5

Building 5 Turn Tracker
Maintenance
August 9 – 10
Painting
August 11 – 12
Cleaning
August 13 – 14
Carpet Cleaning
August 17
Final Inspection
August 16
Maintain move-in ready
August
17 – 21

Building 6

Building 6 Turn Tracker
Maintenance
August 8 – 12
Painting
August 13 – 14
Cleaning
August 14 – 15
Carpet Cleaning
August 18
Final Inspection
August 18
Maintain move-in ready
& Maintenance Go baccks
August
18 – 21

Building 7

Building 7 Turn Tracker
Painting
July 31 – August 2
Maintenance
August 10 – 15
Cleaning
August 16 – 17
Carpet Cleaning
August 19
Final Inspection
August 18
Maintain move-in ready
& maintenance go backs
August
19 – 21
