SCC Turn Tracker

South Campus Commons same-bed residents can use this page to help them prepare for the lease transition period.  The calendars below are a tentative plan for when each building will get each trade for the lease transition period.  Please remember that in preparing over 500 apartments, this plan is fluid and can be affected by the amount of time individual apartments need.  The entry dates can move up or back by a day or two depending on how quickly the work is completed.

As stated in the South Campus Commons lease, entries can happen any day during this time between 8 AM and 8 PM, 7 days a week.  This will include completion of work, inspections, and go-backs and touch ups based on those inspections.

Below the calendars are up-to-date trackers.  These trackers indicate when an entire building is completed; so they may not fully reflect if your individual apartment has been visited for the given trade, yet.  These are updated daily, so there could be a lag from work completed the previous day.  These are meant to give an estimate of where the crews are in the process and do not reflect when teams need to go back to units based on individual inspection results.

The South Campus Commons team thanks you for your cooperation and understanding during the lease transition period, as we all work together to provide a welcoming environment to our incoming residents.

Building 1

Building 1 Turn Tracker

Maintenance

July 27 – 30

 Painting

jULY 31 –    aUGUST 4

Cleaning

August 5-6

Carpet Cleaning

August

10 – 11

Final Inspection

August 8

Maintain move-in ready

& Maintenance Go-backs

August 9 – 17

Building 2

Building 2 Turn Tracker

Maintenance

July 31 –  August 1

Painting

August 3-4

Cleaning

August 6-7

Carpet Cleaning

August 12

Final Inspection

August 8

Maintain move-in ready

And Maintenance Go backs

August

9 – 17

Building 3

Building 3 Turn Tracker

Maintenance

August 2 – 4

Painting

August 5

Cleaning

August 8 – 9

Carpet Cleaning

August 13 – 14

Final Inspection

August 12

Maintain move-in ready

& Maintenance go backs

August

11-17

Building 4

Building 4 Turn Tracker

Maintenance

August 5 – 6

Painting

August 6 – 7

Cleaning

August 9 – 10

Carpet Cleaning

August 14

Final Inspection

August 12

Maintain move-in ready

& Maintenance go backs

August

16 – 21

Building 5

Building 5 Turn Tracker

Maintenance

August 6 – 7

Painting

August 9 – 10

Cleaning

August 11 – 12

Carpet Cleaning

August 15

Final Inspection

August 13

Maintain move-in ready

August

13-17

Building 6

Building 6 Turn Tracker

Maintenance

August – 10

Painting

August 10 – 11

Cleaning

August 13 – 14

Carpet Cleaning

August 16

Final Inspection

August 15

Maintain move-in ready

& Maintenance Go baccks

August

15-17

Building 7

Building 7 Turn Tracker

Painting

July 29 – 31

Maintenance

August 11-13

Cleaning

August 15 – 17

Carpet Cleaning

August 17

Final Inspection

August 16-17

Maintain move-in ready

& maintenance go backs

August

16 – 17